SANTALUCES SENIOR HIGH
Project Number:  1611-1005
Project Title: 
Drainage Improvements
Administrator: Jim Kunard Coordinator: Mark Black
Architect: Keith & Associates, Inc.  
Contractor:Wynn & Sons Environmental Construction Co., Inc.    
Application Date: 04/13/2010 Completion Date:  05/24/2011
C   E   A   R   M   D   O  
P
03/08/2011
 

Design Number: 
Facility: 
SANTALUCES SENIOR HIGH
Project Number:  1611-2222
Project Title: 
ADA Title II Compliance
Administrator: Thomas Hogarth Coordinator: Victor Chodora
Architect: NOT APPLICABLE  
Contractor:Facilities Services    
Application Date: 11/18/2009 Completion Date:  
C   E   A   R   M   D   O  
A
11/18/2009
 

Design Number: 
Facility: 
SANTALUCES SENIOR HIGH
Project Number:  1611-1701
Project Title: 
CSIR Modifications
Administrator: Dorothy Banaszewski Coordinator: Jim Wally
Architect: Harvard Jolly Architects, Inc.  
Contractor:Robling Architecture Construction, Inc.    
Application Date: 04/20/2017 Completion Date:  09/21/2017
C   E   A   R   M   D   O  
P
04/24/2017
 

Design Number: 
Facility: 
SANTALUCES SENIOR HIGH
Project Number:  1611-1702
Project Title: 
Verizon Dark Fiber Upgrade
Administrator: Chad Girard Coordinator:
Architect:  
Contractor:ComStruct Services Inc.    
Application Date: 02/28/2017 Completion Date:  03/31/2017
C   E   A   R   M   D   O  
P
03/07/2017
 

Design Number: 
Facility: 
SANTALUCES SENIOR HIGH
Project Number:  1611W1404
Project Title: 
Cafeteria Renovations-Rm. Identification Signs
Administrator: Angel Garcia Coordinator:
Architect: NOT APPLICABLE  
Contractor:Fast Signs    
Application Date: 10/07/2015 Completion Date:  11/13/2015
C   E   A   R   M   D   O  
P
10/14/2015
 